Market Notice

July 9, 2008

 

Requested Client Action

Information Only

Categories

Legal/ Regulatory

Market Operations

 

 

2009 Import Capability Assignment Process - Step 6 and 7

___________________________________________________

 

Summary

The CAISO has posted the information required by Step 6 of the Import Capability Assignment Process (CAISO Tariff Section 40.5.2.2.1).   The CAISO will also be sending to Scheduling Coordinators via e-mail the information required by Step 7 on July 9, 2008

___________________________________________________

 

Main Text 

The California ISO (CAISO) assigns import capability to Load Serving Entities through their respective Scheduling Coordinators for compliance with resource adequacy requirements for 2009 through a multi-step process under CAISO Tariff Section 40.5.2.2.1. The CAISO has completed Steps 6 and 7.

 

Step 6 Requirement

CAISO posted on July 8 a document, entitled 2009 Assigned and Unassigned RA Import Capability on Branch Groups into the CAISO Control Area after Step 6, containing the following information:

 

 

The document is located on the Stakeholders Initiative/Current Initiatives/Resource Adequacy/Import Allocation web page at: http://www.caiso.com/1c44/1c44b2dd750.html.

 

Step 7 Requirement

CAISO will send an email on July 9 to each Load Serving Entity, through its respective Scheduling Coordinator, the following information: 

 

___________________________________________________

 

For More Information Contact

Catalin Micsa at cmicsa@caiso.com 916.608.5704

Grant Rosenblum at grosenblum@caiso.com 916.608.7138

 

The California ISO strives to be a world-class electric transmission organization built around a globally recognized and inspired team providing cost-effective and reliable service, well-balanced energy market mechanisms, and high-quality information for the benefit of our customers.