Summary

This Notice informs stakeholders that the implementation date of the new “D1” CAISO Control Area Network Model has changed from June 26, 2008 to July 3, 2008.

___________________________________________________

 

Main Text

The new implementation date of the “D1” California ISO (CAISO) Control Area Network Model has changed from June 26, 2008 to July 3, 2008.  The implementation date is being pushed out one week to include additional impedance updates.  The new network model “D1” focuses upon establishment of new resources and is scheduled for production release on July 2, 2008 for trade date of Thursday, July 3, 2008, HE01.

 

CAISO has posted a new white paper entitled “Proposal for CAISO Control Area Network Model Revision (D1)”, to its website at http://www.caiso.com/docs/2005/09/30/2005093009575924103.html. Please refer to the white paper for more information.

__________________________________________________

 

For More Information Contact

Mike Boas, CAISO Model and Contract Implementation, at mboas@caiso.com or Troy Siegel, CAISO Market Operations, at tdsiegel@caiso.com

The California ISO strives to be a world-class electric transmission organization built around a globally recognized and inspired team providing cost-effective and reliable service, well-balanced energy market mechanisms, and high-quality information for the benefit of our customers.

151 Blue Ravine Road, Folsom, CA 95630

Update profile or unsubscribe

EA/ComPR/IPS/ca