Market
Notice
June 11, 2008
|
Requested Client Action Mark Your Calendar Request for Comment RSVP |
Categories
Grid Operation
Legal/ Regulatory
Market Rules and Market Design
Additional GIPR Stakeholder Meeting
___________________________________________________
Summary
The CAISO will hold an additional Generation Interconnection Process Reform (GIPR) Stakeholder Meeting on July 1, 2008 to further discuss proposed CAISO Tariff revisions to implement the GIPR. Please RSVP by June 27. Comments on the tariff revisions are due June 17 and final tariff comments are due July 8, 2008.
___________________________________________________
Main Text
The California ISO (CAISO) held a GIPR Stakeholder Meeting on June 10, 2008 to discuss proposed CAISO Tariff revisions to implement the GIPR. Comments in response to this June 10 meeting and the posted tariff revisions are due to isoqueue@caiso.com by close of business (COB) June 17, 2008.
CAISO anticipates posting a set of tariff revisions to its website at http://www.caiso.com/1f42/1f42c00d28c30.html by COB June 24, 2008.
CAISO will hold an additional GIPR Stakeholder Meeting on July 1, 2008 to further discuss the proposed Tariff revisions. Please RSVP to SMC@caiso.com by COB June 27, 2008.
Stakeholders should submit final tariff comments to isoqueue@caiso.com by COB July 8, 2008.
Meeting Details
Date: Tuesday, July 1, 2008
Time: 10:00 a.m. to 4:30 p.m. Pacific Time
Location: CAISO Offices, 101 Blue Ravine Road, Folsom, California
Teleconference Information
Dial-in Number: 800-288-8960
International Dial-in: 612-234-9960
Web Conference Information
Web Address: www.webmeeting.att.com
Meeting Number: 8662054243
Access Code: 3459258
Remaining GIPR Schedule
June 17, 2008 Stakeholder GIPR tariff language comments due COB at isoqueue@caiso.com
June 24, 2008 CAISO to post next draft of GIPR tariff language revisions
July 1, 2008 Tariff language stakeholder meeting at CAISO Offices in Folsom, CA
July 8, 2008 Stakeholder final GIPR tariff comments due COB at isoqueue@caiso.com
July 9, 2008 GIPR proposal taken to CAISO Governing Board
Mid July GIPR tariff language submitted to FERC for approval
___________________________________________________
For More Information Contact
Stephen Rutty at srutty@caiso.com
The California ISO strives to be a world-class electric transmission organization built around a globally recognized and inspired team providing cost-effective and reliable service, well-balanced energy market mechanisms, and high-quality information for the benefit of our customers.
151 Blue Ravine Road, Folsom, CA 95630
EA/ComPR/IPS/ds