Summary:  The CAISO is continuing its analysis of Must Offer Waiver Denials during the period June 2006 through February 28, 2007 in accordance with the RCST Settlement.  Given the scope of this evaluation process, the CAISO cannot commit to a specific date for the release of the Significant Event / Repeat Waiver Denial Reports contemplated in the Settlement.  The CAISO will provide another update on this process on June 15, 2007. 

___________________________________________________

 

Main Text:  As the California ISO (CAISO) indicated in a market notice issued on March 26, 2007, the CAISO is analyzing Generator Must Offer Waiver Denials (MOWD) that occurred during the period June 1, 2006 through February 28, 2007 for purposes of preparing weekly Significant Event/Repeat Waiver Denial Reports as contemplated in the Reliability Capacity Services Tariff (RCST) Settlement.  The CAISO is conducting a MOWD evaluation for every fourth calendar day in which the CAISO issued a MOWD to a Must Offer Generator.  As part of its analysis, the CAISO will determine whether or not any Significant Events occurred during this period that might warrant RCST designations under the RCST Settlement.

 

The CAISO is working to complete the MOWD evaluation process and prepare the Significant Event/Repeat Waiver Denial Reports as soon as possible but, given the scope of the project, the CAISO is unable to specify a date by which this process will be completed.  The CAISO will issue a Market Notice on June 15, 2007 updating the market on the status of its MOWD evaluations.

 

The CAISO notes that the Significant Event/Repeat Waiver Denial report process does not affect the timeline for compensating  units that were committed under MOWD retroactively to June 1, 2006.  The current timeline for Settlements’ completion of this process will be provided in a separate Market Notice.

___________________________________________________

 

For More Information Contact:  Troy Siegel, Market Operations, tsiegel@caiso.com

 

 

 

The California ISO strives to be a world-class electric transmission organization built around a globally recognized and inspired team providing cost-effective and reliable service, well-balanced energy market mechanisms, and high-quality information for the benefit of our customers.

 

EA/ComPR/IPS/ds