CALIFORNIA ISO MARKET
NOTICE
Requested
Client Action: Information Only
Date of
Distribution: April 24,
2006
Categories: Grid Operation, Legal and Regulatory,
Market Rules and Market Design
Subject: Generating Unit Availability Reporting
Requirements
___________________________________________________
Summary: This notice reminds Market Participants
of the requirements to report Generating Unit availability. Beginning with Trading Day May 15, 2006,
failure to comply with Tariff requirements may be financially sanctioned.
___________________________________________________
Main
Text: The California ISO (ISO) Enforcement
Protocol requires Market Participants to comply with the Tariff requirements to
report Generating Unit availability, including:
·
Report
“any Outage of a Generating Unit subject to Section 4.6 of the ISO Tariff within
thirty (30) minutes after the Outage occurs.” See ISO Tariff
37.4.1.
·
Schedule
and obtain ISO approval of all outages in accordance with the Tariff, except for
Forced Outages. This includes
obtaining final approval from the ISO Control Center on the day a Planned Outage
commences. See ISO Tariff
37.4.2.
·
Provide
explanations of Forced Outages, including a description of the equipment
failure or other cause and the remedial actions taken, within
two working days of the commencement of a Forced Outage. Market Participants are also to provide
additional information that may be requested by the ISO to review the
explanation in the timeframe specified in the ISO’s request. See ISO Tariff
37.4.3.
The ISO’s operating procedure that
addresses scheduling and notification of Outages, “T-113 Scheduled and Forced
Outages,” is posted at http://www1.caiso.com/thegrid/operations/opsdoc/transmon/index.html. Market Participants are to use the SLIC
Web Client to schedule and obtain approval of planned Outages, report Forced
Outages, and provide explanations of Forced Outages. SLIC Web Client instructions and the
Forced Outage reporting requirements are posted at http://www1.caiso.com/docs/2001/02/01/2001020108211325518.html. This material includes guidelines
regarding the information required as part of an explanation of a Forced
Outage.
The ISO Department of Market
Monitoring will issue sanctions pursuant to the ISO Tariff Enforcement Protocol
beginning with the May 15, 2006 Trading Day for failure to comply with these
requirements.
___________________________________________________
For More
Information Contact:
For more information on Forced
Outage Reporting, contact Rod Wheeler, Outage Management at 916-351-4433 or rwheeler@caiso.com.
For more information on the
Enforcement Protocol contact Brad Cooper, DMM, at 916-608-7156 or bcooper@caiso.com.
The California ISO strives to be a
world-class electric transmission organization built around a globally
recognized and inspired team providing cost-effective and reliable service,
well-balanced energy market mechanisms, and high-quality information for the
benefit of our customers.
EA/ComPR/IPS/ds